October 5, 2022 – Final design activities are underway and will extend into 2022. These activities include right-of-way negotiations with affected property owners, utility coordination, wetland mitigation plan preparation, and environmental permitting.
Through coordination with property owners, the geometry of the northern approach to the roundabout was revised. The updated plan is shown below. Upon completion of right-of-way acquisitions and environmental permitting approval from the appropriate agencies, the project is anticipated to be advertised for construction in winter 2022. Construction is anticipated to start in summer 2023.